Woodside – KGP Turbine Control System Upgrade

The project objective is to address the obsolescence risks to operations by implementation of system upgrades to the Turbine Control Systems, HMI and Historian.
Karratha Gas Plant Turbine Controls Systems consist of various generations of Baker Hughes General Electric technology including Speedtronic Mark V and Mark VI systems.
The various TCS, HMIs and historians are required to support KGP operations until the End of Field Life (EOFL) for the plant area they are supporting. These systems and associated panel active components are at differing stages in their product life cycles and with EOFL in mind will be upgraded.
The first stage of the project is nearing completion with TechRefresh of HMI’s and Historians completed on LNG1, LNG2, LNG5, and power generation GT4001 through GT4006. LNG3, and Domgas will follow in the first half of 2020.

2016 – Ongoing